OEE Systems
ASI has its own OEE System that can be integrated into your controls or as a stand alone system.
The OEE calculation is based on the three OEE Factors: Availability, Performance, and Quality.
Availability
Availability takes into account Down Time Loss, and is calculated as:
Availability = Operating Time / Planned Production Time.
Performance
Performance takes into account Speed Loss, and is calculated as:
Performance = Ideal Cycle Time / (Operating Time / Total Pieces)
Ideal Cycle Time is the minimum cycle time that your process can be expected to achieve in optimal circumstances. It is sometimes called Design Cycle Time, Theoretical Cycle Time or Nameplate Capacity.
Since Run Rate is the reciprocal of Cycle Time, Performance can also be calculated as:
Performance = (Total Pieces / Operating Time) / Ideal Run Rate
Performance is capped at 100%, to ensure that if an error is made in specifying the Ideal Cycle Time or Ideal Run Rate the effect on OEE will be limited.
Quality
Quality takes into account Quality Loss, and is calculated as:
Quality = Good Pieces / Total Pieces
OEE
OEE takes into account all three OEE Factors, and is calculated as:
OEE = Availability x Performance x Quality
In order to improve OEE, a range of data needs to be collected including equipment, machine, production efficiency, waste, downtime, operators, orders, shifts, events, products, causes, frequency and reasons.